
Florida Renovators, Inc. - (727) 531-9520
Florida License Number-CGC016919
Reasons Estimating Fails
-
The owner lacks clarity on what needs to be repaired, constructed, or completed.
-
The estimated costs exceed the owner's expectations.
-
The written specifications are not formatted in a way that the owner finds acceptable.
-
There was reliance on guesswork for comparisons.
-
The owner is overly focused on the final cost and disputes any unspecified extras not included in the contract.
-
The owner approaches the project as if they are seeking a bargain, similar to shopping at Wal-Mart.
-
The contractor did not obtain written approval for the scope of work to be performed.
-
The owner assumes the contractor will meet all expectations, regardless of what was specified.
-
The owner believes that all permitting issues and project conditions are included in the original estimate.
-
The owner expects the contractor to absorb any unforeseen costs, thinking they have already paid a substantial amount.
-
The owner did not review or understand the design drawings.
-
The contractor failed to have the owner sign the contract and plans.
-
The contractor must ensure the owner signs the design plans, which should be referenced in the contract and dated.
-
The contractor assumed that the building plans would be approved by the building department, which influenced the project cost.
-
The design drawings contain numerous errors, and the owner is reluctant to accept responsibility for additional costs.
-
The contractor initiated the project on a design/build basis.
-
Existing conditions changed after construction commenced.
-
The owner did not allocate a budget for unforeseen issues and requirements.
-
The contractor did not communicate that the project is a "PROCESS" that requires completion.
-
There are no contractual specifics documented for undefined issues, such as existing conditions like termite damage, structural failures, weather conditions, or operational challenges.
-
Payment and project stage approvals are based on a draw schedule for work completed.
-
The contractor does not manage and control the project according to the contractual costs involved.
-
Job reports are not regularly documented.
-
Communication between the contractor and the owner has not been consistently maintained.
-
The contractor works for the owner and oversees the project.
-
Trade contractors operate under the general contractor's supervision.
-
Instruction sheets are signed off for approval.